Warsaw, Rakowiecka – Pulawska Str.
2024
CONTRACTOR: Balzola Polska sp. z o.o.
QUANTITY: 1 440 m2 | 57,57 mb
PRODUCT: MATA | PROFILE
TYPE: 500/25 | BAR
The construction of the junction from Pulawska Street into Rakowiecka Street – due to limited space and the required short lead time – was a challenge for the contractor and the people of Warsaw. Bearing in mind the required technical parameters and the immediate availability of the product (Epufloor ensured delivery of the first batch of mats in a record time of 24 hours from the date of the order), the Contractor decided to use Eputrack mats. This allowed the work to be completed within the timeframe previously assumed.